Solving capacity problems
The schedule view uses a calendar and colour codes to show you who is at capacity, and when. You can find the Schedule page under the Scheduli...
Thu, 14 Nov, 2024 at 9:39 PM
If the deadline is flexible, you could solve this problem by changing the deadline, and having the project finish later. This means he’s spending less ti...
Thu, 14 Nov, 2024 at 9:39 PM
If extending the deadline is not an option, you can take the entire job off Aurif, and give it to someone who has capacity to do it. If we look a...
Thu, 14 Nov, 2024 at 9:40 PM
Splitting a job between staff members is another way to handle this problem. 80 hours over the next couple weeks may put Aurif over capacity, but he prob...
Thu, 14 Nov, 2024 at 9:40 PM